project milestones

2020

Water 2120 Plan
Program Identified

2022

Project Design Consultant Engaged

2023

Project Visioning Complete

2024

Basis of Design Report Complete

2025

Preliminary Engineering Report (PER) Complete

Preliminary Design Complete

Construction Manager at Risk (Contractor) Engaged

2026

Environmental Studies Ongoing

PER New Mexico Environmental Department Approval

Upcoming Milestones*

  • Design Complete - July 2027
  • Construction Notice to Proceed - November 2027
  • Substantial Completion - November 2030
  • Commissioning - Spring 2031

*Design schedule and construction notice to proceed are subject to change depending upon regulatory approval process.